MX Robotics delays Indian solar storage project again

The warehouse system, worth more than 40% of MX Robotics' 2025 revenue, is now due more than 15 months after its first deadline.

Share
Tall orange and blue racking in an automated warehouse, with stacker-crane masts running between the aisles.
A stacker crane and racking in an MX Robotics automated storage and retrieval system. Photo: MX Robotics

MX Robotics (엠엑스로보틱스), a South Korean maker of automated warehouses, has delayed a third time a 63.2 billion won (about US$47 million) storage and retrieval system it is building in India for Reliance New Solar Energy, an Indian solar-panel maker. By our calculation, the job is worth more than 40% of its 2025 revenue.

The original 2024 filing, made under its former name, SMCore, set completion for Dec. 12, 2025. Corrections moved that to Aug. 11, 2026, then Dec. 31, 2026. A third correction, filed Nov. 24, moved it to March 31, 2027, more than 15 months past the original date. Each cites "a change in delivery date due to local circumstances."

The company's quarterly report lists the project in two parts, 88.9% and 90.6% complete by cost at Sept. 30. Neither the contract filings nor the quarterly report mentions a dispute. The report sets nothing aside against the risk of not being paid on its Reliance contracts. The filings don't say how much Reliance has paid.

Seoul-based MX Robotics had an operating loss of 8.0 billion won (about US$6 million) on revenue of 149.1 billion won (about US$112 million) in 2025. Its operating loss for January through September 2026 was 6.2 billion won (about US$5 million), on revenue of 82.8 billion won (about US$62 million).

Reliance Industries, whose most recent annual revenue MX Robotics' filing gives as 192.4 trillion won (about US$124 billion), placed another order in July, worth 19.5 billion won (about US$13 million), for logistics automation in solar-panel production. India accounted for about half of MX Robotics' export sales from January through September 2026, by our calculation.

The filings say only that the warehouse is in India, and give no reason for the delays beyond local circumstances. Reliance is starting up its solar complex at Jamnagar, in Gujarat, in stages. By July it had made about 1 gigawatt of solar modules toward a 20-gigawatt annual capacity goal, it told analysts. It said then that its wafer pilot plant was finished and that it would begin commissioning gigawatt-scale wafer production in the next few quarters.

Sources (9)

  • DART — MX Robotics supply-contract correction
  • DART — MX Robotics supply-contract correction
  • DART — SMCore supply-contract correction
  • DART — SMCore supply-contract filing
  • DART — MX Robotics quarterly report
  • DART — MX Robotics supply-contract filing
  • Reliance Industries — Q1 FY2027 call transcript
  • Reliance Industries — Q4 FY2026 call transcript
  • MX Robotics — logistics automation page

Editor: Ian Lamont